Augsburger Road pathway project slated to start Sept. 21

Project completion date is Oct. 31

Work on the Augsburger Road pathway project will begin on Sept. 21. Jamie Mehaffie, village administrator, will update Bluffton council on the project on Monday.

COUNCIL AGENDA IS IN ATTACHMENT AT BOTTOM OF STORY -

When completed, the pathway will exend from Bentley Road (north side of Augsburger), to Maple Crest. A completion date is Oct. 31.

Mehaffie said that initially, construction will be limited to the areas of the project that are outside of the Bluffton University Nature Preserve.

There are trees that will be removed in October in the nature preserve area. Tree Tech will remove those trees beginning Oct. 3. After those trees are removed the pathway work will continue on the nature preserve land.

 