Bluffton council will get an update on several village projects at Monday’s council meeting.

Among items on the agenda include:
• The Jefferson Street bridge will be grooved on Tuesday, as the asphalt was installed today. Also, on Tuesday will be street line striping. Once completed the roadway will open.

• New playground equipment for the Buckeye park playground arrived last week. It will be installed on Tuesday.

• Leaf pick up will begin this week.

• Twenty-six ADA curb ramps were completed in the village in 2019.

• A priority list for sidewalk evaluation is underway.

• Phase II (2020) of the Jefferson Street improvement project will include meetings with property owners – to be scheduled this week.

• Discussion of State and U.S. Bike Route System through Bluffton.

These and other items on the agenda are in the council packet attached at the bottom of this story.