You are here

I-75 construction update south of Bluffton

Work on Interstate 75 south of Bluffton will experience distruptions next week. Here's the update.

NEW IMPACT
• Beginning Aug. 7, northbound passing lane at SR 696, Beaverdam, will be shifted to the southbound side.

• SR 696 exit ramp from I-75 northbound will close Aug. 11 for five days for a culvert replacement.

• Detour:­­­­­­­­­­­ I-75 northbound to SR 103/Bentley Rd. to I-75 southbound back to SR 696 (see map).

CONTINUING IMPACTS
• Beginning Aug. 4, both lanes of I-75 southbound at SR 696, Beaverdam, will be shifted onto new pavement.

• Nighttime lane restrictions, 7 p.m. – 7 a.m., resumed on July 19 and will continue for approximately two months for paving operations.

 

Section: