New emergency department entrance door installed at hospital this week
Several new construction steps are part of the June 14 Bl;uffton Hospital renovation. Work projects planned this week follow:
* Charles Construction will be installing the new exterior Emergency Department entrance door.
* As they prepare to install the new interior ER entrance door, Facility Services will begin to remove the wall shelves and fixed desk at the former ER Nurse Station.
* The patient monitors will be relocated as a wall mount within the existing Emergency Department.
* After the desk is removed, a fireproof vinyl barrier will be put in place to allow the contractor to install the interior Emergency Department door. This will keep the current ER area operational.
* For the surgery area, work begins with setting the footers and foundation in the former garage area.
* The new buildings are being constructed following U.S. Green Building Council guidelines. The intent is to achieve LEED (Leadership in Energy and Environmental Design) certification upon completion.
Stories Posted This Week
Thursday, September 4, 2025
- Pirate girls tennis loss to Shawnee
- Lugabill Rd. closed for paving on Sept. 4
- Pirate volleyball loss at Liberty-Benton
- Pirate boys golf win vs. Ada
- Ultra-processed foods: Impact on children’s health
- Check out Bluffton Public Library’s September 2025 programs and services
- Active shooter training to be held at Apollo Career Center
- Etc. Volunteers Garden created by Tim Byers
- Letter: Darrell Groman celebrates 40 years of optometric practice
Wednesday, September 3, 2025
- Obituary for Dawn Inniger Curth
- Pirate boys soccer tie vs. Van Buren
- Gritty Pirate tennis win vs. Defiance
- Pirate volleyball rallies past Arlington
- Bluffton girls soccer pounds Knights
- Pirate golfers edged in tight NWC tri
- President Sider charts Bluffton’s path forward
- Physical therapy technique presentation, Sept. 18