Work on the hospital's second floor continues next week
Steel erection and framing of the two-story addition at the Bluffton Hospital continues next week. This addition will house the new emergency department and other services. As part of the framing, masonry block installation continues for the interior elevator and stairwell.
Roofing is being finished and interior framing of new walls and hanging HVAC duct work for the new operating room continues.
Work on two emergency exit ramps from our existing building is well under way. One is on the alley (west) side and the other will replace the steps near the medical/surgical exit from the first floor.
Major construction equipment and delivery trucks will continue to cause periodic traffic restrictions. The hospital staff asks that persons drive carefully and protect the safety of the construction workers.
Stories Posted This Week
Sunday, August 3, 2025
Saturday, August 2, 2025
Friday, August 1, 2025
Thursday, July 31, 2025
- Bluffton University names Dr. J. Alexander Sider as next President
- GLP-1s and weight loss: Impact on muscles
- Check out August 2025 at Bluffton Public Library
- Discovery Days prize drawing results, check your tickets
- Wesley “Wes” Allen Leightner worked for Phillips
- How floundering Cards should deal at deadline
Wednesday, July 30, 2025
- Letter: BOHS work night at the Depot, July 30
- County park district considers name change, invites feedback
- Teen vaccine clinic at Bluffton Middle School, August 18
- State of Ohio expands commercial truck parking at US 30 rest areas
- National Night Out celebration is August 5
- Bluffton council hears neighbor concerns about proposed school practice field
- GROB Systems to host 5-AXIS LIVE! with 21 industry partners on Aug. 5