Work on the hospital's second floor continues next week
Steel erection and framing of the two-story addition at the Bluffton Hospital continues next week. This addition will house the new emergency department and other services. As part of the framing, masonry block installation continues for the interior elevator and stairwell.
Roofing is being finished and interior framing of new walls and hanging HVAC duct work for the new operating room continues.
Work on two emergency exit ramps from our existing building is well under way. One is on the alley (west) side and the other will replace the steps near the medical/surgical exit from the first floor.
Major construction equipment and delivery trucks will continue to cause periodic traffic restrictions. The hospital staff asks that persons drive carefully and protect the safety of the construction workers.
Stories Posted This Week
Sunday, June 14, 2026
Saturday, June 13, 2026
Friday, June 12, 2026
- Ada Icon headlines, June 12
- Blanchard River Watershed Partnership hosts 5K trail run on July 25
- Beaverdam to begin water treatment plant repairs
- Save the date: Declaration of Independence reading, July 8
- Bluffton Police answer 630 calls for service in May 2026
- Great wealth disparity and our eroding democracy
Thursday, June 11, 2026
- Ada Icon headlines, June 11
- Splitting headache: Fasting and migraines
- Pamela Ann Bricker was a social worker
- Bluffton Community Garage Sales, June 18-19-20
- Open and improved Elm St. segment
- Ultimate car seat guide recommended by Bluffton police
- Senior Center's June community meal shifts to summer schedule