Augsburger Road pathway project slated to start Sept. 21
Work on the Augsburger Road pathway project will begin on Sept. 21. Jamie Mehaffie, village administrator, will update Bluffton council on the project on Monday.
COUNCIL AGENDA IS IN ATTACHMENT AT BOTTOM OF STORY -
When completed, the pathway will exend from Bentley Road (north side of Augsburger), to Maple Crest. A completion date is Oct. 31.
Mehaffie said that initially, construction will be limited to the areas of the project that are outside of the Bluffton University Nature Preserve.
There are trees that will be removed in October in the nature preserve area. Tree Tech will remove those trees beginning Oct. 3. After those trees are removed the pathway work will continue on the nature preserve land.
Stories Posted This Week
Tuesday, August 12, 2025
Monday, August 11, 2025
- Coletta Irene Mullenhour worked at M&R Plumbing and Heating
- New Findlay Community Orchestra invites string players
- Children's tryouts for ONU Holiday Spectacular on Sept. 7
- 2025 History Day showcases a love of Bluffton, fascination with trains
- Schumacher Homestead to be featured on WBGU travel program
- More about Bluffton and railroads
Sunday, August 10, 2025
Saturday, August 9, 2025
- Reminder of 1899 Depot move and refurbishment by Bluffton Sportsmen's Club
- JAMPD to retain Johnny Appleseed identity following poll
- Board of Elections lists November 2025 candidates for school board, township trustees and village council
- Bluffton chamber to host AI Lunch & Learn with Courtnee R. Morris
- Weekend Doctor: Family Estrangement on the Rise