Augsburger Road pathway project slated to start Sept. 21
Work on the Augsburger Road pathway project will begin on Sept. 21. Jamie Mehaffie, village administrator, will update Bluffton council on the project on Monday.
COUNCIL AGENDA IS IN ATTACHMENT AT BOTTOM OF STORY -
When completed, the pathway will exend from Bentley Road (north side of Augsburger), to Maple Crest. A completion date is Oct. 31.
Mehaffie said that initially, construction will be limited to the areas of the project that are outside of the Bluffton University Nature Preserve.
There are trees that will be removed in October in the nature preserve area. Tree Tech will remove those trees beginning Oct. 3. After those trees are removed the pathway work will continue on the nature preserve land.
Stories Posted This Week
Friday, September 5, 2025
- NEW DATE Thayer Rd. closure for bridge repair begins Sept. 15
- Beavers sports roundup, Aug 29-Sept 4
- Pirate boys soccer shut out by Ottoville
- Pirate girls soccer edged by Bath
- Pirate volleyball sweeps Elmwood
- 1-year anniversary celebration of Elm St. businesses on Sept. 6
- Sugden and Windle finalists in CreativeOhio Champion Advocacy Awards
Thursday, September 4, 2025
- Pirate girls tennis loss to Shawnee
- Lugabill Rd. closed for paving on Sept. 4
- Pirate volleyball loss at Liberty-Benton
- Pirate boys golf win vs. Ada
- Ultra-processed foods: Impact on children’s health
- Check out Bluffton Public Library’s September 2025 programs and services
- Active shooter training to be held at Apollo Career Center
- Etc. Volunteers Garden created by Tim Byers
- Letter: Darrell Groman celebrates 40 years of optometric practice
Wednesday, September 3, 2025
- Obituary for Dawn Inniger Curth
- Pirate boys soccer tie vs. Van Buren
- Gritty Pirate tennis win vs. Defiance
- Pirate volleyball rallies past Arlington
- Bluffton girls soccer pounds Knights
- Pirate golfers edged in tight NWC tri
- President Sider charts Bluffton’s path forward
- Physical therapy technique presentation, Sept. 18