West Elm Street project starts in early October
Roadwork will begin on the West Elm Street project in early October, according to Jesse Blackburn, village administrator. The project covers Elm from Spring to Rosenberger Drive.
Blackburn brought Bluffton council members up to date on the project on Sept. 10.
The project has two phases.
• Water work phase
October to December –
• Installation of an 8-inch water main, creek crossing, new service lines, new meter settings where required and new fire hydrants.
• Trenches from work performed will be temporarily paved, road is planned to be closed during construction, maintained for local traffic.
• Street work phase
March to June 15, 2019 –
Complete road reconstruction, sidewalks, curb, 4-foot tree lawn between sidewalk and curb and installation of catch basin.
Stories Posted This Week
Friday, August 22, 2025
Thursday, August 21, 2025
- Cheryl Anise Pingle worked at Dayspring Church
- Lima Highway Patrol OVI checkpoint August 22
- Pirate VB sweeps Rockets
- Pirate boys drop golf tri
- Bluffton Board of Education hears neighbor comments on practice field, approves Lawn Ave. plan
- United Way of Greater Lima holds 9th annual Day of Caring on Sept. 5
- Village of Beaverdam announces committee meetings
- An amazing sign of fall 2025
- August 23 Bluffton Cars & Coffee
- If You Could Read My Mind: GLP-1s and memory
Wednesday, August 20, 2025
Tuesday, August 19, 2025
- Village of Bluffton reminder of electric aggregation provider, solicitor permit requirements
- Previews of Bluffton Senior Center trips for 2026
- English Lutheran Church to provide Community Meal, August 21
- Welcome back to Bluffton Beavers
- Pirate football reloads for run at NWC crown
- Pirate volleyball swept by Shawnee
- Pirate girls golf loss to Fort Loramie
- Pirate girls tennis edged by Spartans
- Made In Ada Wilson Football Festival kicks of season August 23