West Elm Street project starts in early October
Roadwork will begin on the West Elm Street project in early October, according to Jesse Blackburn, village administrator. The project covers Elm from Spring to Rosenberger Drive.
Blackburn brought Bluffton council members up to date on the project on Sept. 10.
The project has two phases.
• Water work phase
October to December –
• Installation of an 8-inch water main, creek crossing, new service lines, new meter settings where required and new fire hydrants.
• Trenches from work performed will be temporarily paved, road is planned to be closed during construction, maintained for local traffic.
• Street work phase
March to June 15, 2019 –
Complete road reconstruction, sidewalks, curb, 4-foot tree lawn between sidewalk and curb and installation of catch basin.
Stories Posted This Week
Sunday, June 7, 2026
Saturday, June 6, 2026
Friday, June 5, 2026
- Stay tuned for Pirate action at OHSSA state track and field coverage
- Ada Icon headlines, June 5
- Wheeler graduates from Ohio Bankers League Bank Leadership Institute
- Ellerbrock awarded Lima Memorial Nursing Alumnae Scholarship
- Pirate speedsters Wright and Miller each advance to 2 state finals
- Golfers, sponsors invited to support American Legion fundraiser
- Letter: Alternatives to Village mosquito fogging
Thursday, June 4, 2026
- Eileen Ruth Garmatter was a homemaker
- Elnore Ruth (Rosenberger) Yost taught at Marimor
- WGTE and WBGU create broadcasting partnership
- ICYMI: May 2026 Bluffton Icon Highlights
- Shoppers' journey with Bluffton Small Business Passport has begun
- Middle and high school student activities at BPL
- Local artist Crumrine to teach Watercolor Workshop at Library
- Lacrosse or La Crosse: Game versus virus
- 2027 Senior Center trip planning, June 11