West Elm Street project starts in early October
Roadwork will begin on the West Elm Street project in early October, according to Jesse Blackburn, village administrator. The project covers Elm from Spring to Rosenberger Drive.
Blackburn brought Bluffton council members up to date on the project on Sept. 10.
The project has two phases.
• Water work phase
October to December –
• Installation of an 8-inch water main, creek crossing, new service lines, new meter settings where required and new fire hydrants.
• Trenches from work performed will be temporarily paved, road is planned to be closed during construction, maintained for local traffic.
• Street work phase
March to June 15, 2019 –
Complete road reconstruction, sidewalks, curb, 4-foot tree lawn between sidewalk and curb and installation of catch basin.
Stories Posted This Week
Tuesday, August 25, 2026
- Carolyn Corle worked for Ohio Northern University
- Pandora's Niese Ag LLC wins 2026 Red Gold Stewardship award
- Goshen College innovation leader to explore AI through a liberal arts lens
- Pirate volleyball loses to Shawnee
- Pirate boys golf sweeps NWC tri
- Figurines and household items recontextualized in "Amusings" exhibit
- Bruce Chesser: A Ceramic Retrospective, Aug. 24-Sept 26
- Bluffton Lions reach 80% of All Abilities Playground fundraising goal
Monday, August 24, 2026
Sunday, August 23, 2026
Saturday, August 22, 2026
Friday, August 21, 2026
- Marjorie Jean (Reams) Montgomery was a homemaker
- Meet the Bluffton Pirate football team, Fall 2026
- Ada Icon stories posted this week, August 17-21
- Aug. 22 Bluffton Cars & Coffee reminder
- Pirate girls soccer shuts out Anna in home opener
- Pirate volleyball win vs. Wildcats
- Pirate boys soccer rallies past Archbold
- Capture the essence of Bluffton in photos
- Pirate girls golf places 9th at SJCC Invite
- Call for actors for Dillinger reenactment on October 10