West Elm Street is down to one lane
West Elm Street between Rosenberger Drive and Spring Street is now a one-lane street due to water main installation.
The project has two phases.
• Water work phase
October to December –
• Installation of an 8-inch water main, creek crossing, new service lines, new meter settings where required and new fire hydrants.
• Trenches from work performed will be temporarily paved, road is planned to be closed during construction, maintained for local traffic.
• Street work phase
March to June 15, 2019 –
Complete road reconstruction, sidewalks, curb, 4-foot tree lawn between sidewalk and curb and installation of catch basin.
Stories Posted This Week
Thursday, August 21, 2025
- Cheryl Anise Pingle worked at Dayspring Church
- Lima Highway Patrol OVI checkpoint August 22
- Pirate VB sweeps Rockets
- Pirate boys drop golf tri
- GriefShare support group continues on Thursday evenings
- Bluffton Board of Education hears neighbor comments on practice field, approves Lawn Ave. plan
- United Way of Greater Lima holds 9th annual Day of Caring on Sept. 5
- Village of Beaverdam announces committee meetings
- An amazing sign of fall 2025
- August 23 Bluffton Cars & Coffee
- If You Could Read My Mind: GLP-1s and memory
Wednesday, August 20, 2025
Tuesday, August 19, 2025
- Village of Bluffton reminder of electric aggregation provider, solicitor permit requirements
- Previews of Bluffton Senior Center trips for 2026
- English Lutheran Church to provide Community Meal, August 21
- Welcome back to Bluffton Beavers
- Pirate football reloads for run at NWC crown
- Pirate volleyball swept by Shawnee
- Pirate girls golf loss to Fort Loramie
- Pirate girls tennis edged by Spartans
- Made In Ada Wilson Football Festival kicks of season August 23