In late March, The Icon visited the bridge project that crosses Hog Creek on County Line Road - Hardin County Road 15, south of Bluffton. Here’s a one month progress report.
FROM ADA ICON - The bridge is closed until mid-June while undergoing rehabilitation, according to the Hardin County engineer’s office.
The project, estimated at $220,314, includes work handled by the county and U.S. Bridge of Cambridge. A portion of the cost is covered by a grant from the Ohio Public Works Commission. The U.S. Bridge portion of the project is estimated at $170,314 and the county's share is $50,000.
The removed bridge beams, are in Cambridge, Ohio, undergoing rehabilitation where they will be galvanized. Once they are returned and replaced, the county will reinstall a concrete deck.
In conjunction with the bridge rehabilitation, the county is developing a plan to alleviate flooding of the road at the bridge.
The county hopes to raise the road and then repave County Road 15 from State Route 309 to the county line at County Road 10. This project is slated for the fall.
Click here for March bridge photos.
Stories Posted This Week
Sunday, August 16, 2026
Saturday, August 15, 2026
Friday, August 14, 2026
Thursday, August 13, 2026
- Families and customers create an oral history of memorable Bluffton businesses
- Local students travel to France, Monaco and Italy
- Move on Up: New drug for COVID-19 exposure
- Back to School Days at Bluffton Public Library
- 50 for 250 performances at Bluffton Public Library
- Community meal on August 20 at Bluffton Senior Center
Wednesday, August 12, 2026
- Obituary for centenarian Lois Jean Andreas
- Thomas "Tom" J. Basinger served in the U.S. Army
- President Sider to present Aug. 25 State of the University address
- August 10 council recap: Spending increase for Benroth bridge repairs
- MHCO requests zoning change for construction of senior duplexes
- WIP Wednesday: 1915 kitchen gets a charming DIY remodel