Here's the update on the Green House Project
The March issue of "The Visioneer," which provides updates on the Mennonite Home Communities of Ohio Green House Project is now available for Icon viewers.
House "B" is completely under roof and the rough-in mechanicals (electrical, plumbing, heating/AC, fire suppression) are proceeding rapidly.
House "A" is nearly under roof and then the mechanical rough-ins will begin there as well. There was a point in early December when we thought the project would need to be put on hold until spring.
The mild winter allowed the final cement pads to be poured in early January and pro- gress has continued wonderfully since then.
For more information open the newsletter at the bottom of this story.
Stories Posted This Week
Thursday, August 20, 2026
Wednesday, August 19, 2026
- Aug. 20 program on Monarch butterflies
- Two new teachers introduced at Trinity Lutheran School
- Pirate golfers win wet NWC tri
- Pirate volleyball drops opener to Ottoville
- Pirate girls tennis blanked by Shawnee
- Pirate girls soccer loss vs. Wapakoneta
- Pirate boys soccer beats powerhouse Trojans
- WIP Wednesday: Playful scene in Pandora cafe