2017 sidewalk connectivity price tag: $48,408
Bluffton council approved a 2017 sidewalk connectivity plan anticipated to cost $48,408. The plan was approved on Aug. 14.
Projects in this year’s plan call for 4-foot sidewalks in the following areas:
• East College Avenue gap
• Cherry Street – 465 Cherry to County Line
• Augsburger Bike Path – Riverbend to Hawthorn
• Jefferson Street – beside 204 N. Jackson
This project includes roughly 2,017 linear feet of connectivity. This year’s budget for the project was $50,000.
Here are some further details on these projects:
• East College – 157 Geiger Street placement within the right of way (near road or garage)
• Cherry – Pole obstructions on east side, connectivity on west
• County Line – Placement on edge of right of way
• Augsburger – Riverbend subdivision to Hawthorn
Letters were sent to all property owners affected by this plan. Bids are expected soon.
The connectivity plan was one of three topics discussed by the council streets, alleys, lights and sidewalk committee on July 31.
The other two topics included:
• a food truck ordinance, which had a first reading on Aug. 14.
• Village property on south side of Mustard Seed Café from Main to Lake Street. Survey pins are now in place and a plat and legal description is being worked on.
Stories Posted This Week
Friday, July 18, 2025
Thursday, July 17, 2025
- Cross is Champion in three 2025 State Fair riding events
- July 21 planning commission items include Vine St. closure for practice field
- Forky asks a question: Can a new diet result in significant changes?
- July 22 Twin Town event with Mindelheim, home of GROB-Werke
- Sign up for Bluffton's Got Talent at Bluffton Public Library