Curbing next step in Bluffton Hospital construction project
Pending weather conditions, curbing work should occur mid-week and driveway pours later in the week in construction projects at Bluffton Hospital.
The canopy roof will be roofed, and the second floor windows plus a few around back should be complete.
Eyebrow boarding should start.
Other projects include:
- Work on the corridor to the second floor will begin.
Surgery Area
- With the surgery floor complete, the contractor should finish drywall mud and finish in this area.
- The plumber should finish medical gas piping and electrical connections to the surgery lights and booms.
- Toward the end of the week, painting may begin.
Two story Emergency area
- Drywall hanging should finish.
- Painting of a dozen or so rooms can occur and more ceiling grid will be hung.
- HVAC diffusers should start to be installed and the porcelain tile installation should begin in the restrooms.
Stories Posted This Week
Sunday, October 11, 2026
Saturday, October 10, 2026
Friday, October 9, 2026
- Ada Icon headlines, October 9
- Pirate girls soccer loss vs. St. Marys
- Pirate volleyball sweeps Carey
- “The Trumpet Player” sculpture at Bluffton University receives conservation grant
- October 9 Bluffton Schools athletics lineup, streaming
- Plenty of action at Oct 10 Dillinger robbery reenactment and motorcycle show
- Caitlyn Couch junior piano recital, October 16
- Bluffton community survey opens for Active Transportation Plan
Thursday, October 8, 2026
- Ada Icon headlines on Thursday, October 8
- St. John Bible Church to host "Refocus on Purpose" workshop
- Royal riches: Gout
- Has Bluffton made a birder out of you?
- BPL Afterschool activity: Curious Kids Club
- Book and pizza tasting at Bluffton Public Library
- Final 50 for 250 performance at BPL
- Walking through the Suter Corn Maze
- Resident feedback sought for Regional Transportation Plan
- Bluffton University honors three for service, achievement and leadership