Gas main construction project begins week of January 21
Roads and sidewalks to be impacted, with permanent improvements completed in warmer weather
Starting January 21, 2025, Enbridge Gas Ohio will begin a gas main and service line improvement project to enhance service for Bluffton residents.
Key Details:
• Replacement of approximately 5,200 feet of gas mainline and service connections.
• Estimated duration is up to 50 workdays.
• Our team will coordinate directly with affected residents to ensure a smooth transition to the new gas lines.
• All authorized employees and contractors will carry photo IDs.
• Due to winter weather, temporary concrete will be installed on sidewalks and driveways, with permanent finishing to follow once conditions improve.
From Enbridge Gas Ohio: "We appreciate your patience and understanding as we work to improve your gas service."
For more information about the project, call 1-800-544-5768.
Stories Posted This Week
Thursday, August 14, 2025
Wednesday, August 13, 2025
Tuesday, August 12, 2025
Monday, August 11, 2025
- Coletta Irene Mullenhour worked at M&R Plumbing and Heating
- New Findlay Community Orchestra invites string players
- Children's tryouts for ONU Holiday Spectacular on Sept. 7
- 2025 History Day showcases a love of Bluffton, fascination with trains
- Schumacher Homestead to be featured on WBGU travel program
- More about Bluffton and railroads