Garmatter Street water main project completed
The Garmatter Street water main project is now completed. Jamie Mehaffie, Bluffton village administrator, reported that in addition, it is now tied into the water line at Riley Street.
“When the weather warms up a little bit Beaverdam Contracting will run a pressure test on the line, then complete the disinfection and testing process,” said Mehaffie.
COUNCIL'S MONDAY AGENDA IN ATTACHMENT AT BOTTOM OF THIS STORY.
Once that is completed and passes its test the line will be connected to the new main.
While the contractor is awaiting a temperature warm-up, work will begin on the replacement of a portion of the sanitary line on Garmatter. Work will also begin on the Kibler Street water main replacement project.
Mehaffie will update Bluffton council on that project at Monday’s council meeting.
Several other agenda items are on Monday’s meeting. The entire council packet is an attachment at the bottom of this story.
Stories Posted This Week
Thursday, November 19, 2026
Wednesday, November 18, 2026
Tuesday, November 17, 2026
Monday, November 16, 2026
- Beavers sports roundup, November 9-15
- Home Energy Assistance Program (HEAP) reminder
- Training opportunities expand for Putnam County students
- Cory-Rawson High School Honor Roll for first nine weeks of 2026-2027
- Teens invited to give macrame a try, Nov. 30
- Swiss Heritage Center ribbon cutting and Christmas Open House celebrations