$188,361 street maintenance program on Monday's council agenda
Bluffton council will act on a proposed 2016 street maintenance paving schedule during Monday's meeting.
Heres the street and alley committee 2016 recommendation with estimated costs:
• Kibler Street - $39,697
• Garmatter Street - $57,525
• Harmon Road - Bentley to Garau - $27,781
• Church Street - Main to Jackson - $15,575
• Jackson Street - Church to Elm - $23,970
• Ethan Circle - $16,813
• Striping - $7,000
The original street maintenance budget was 4170,670, however due to a warm winter, council may transer $21,500 from winter funds (salt and snow removal) to the street program.
Several additional items are on Monday's agenda. Those are detailed in the attachement at the bottom of this story.
Stories Posted This Week
Friday, November 6, 2026
Thursday, November 5, 2026
Wednesday, November 4, 2026
- Klausing graduates from Ohio Bankers League Bank Management School
- Joellen Kay Lehman, 46, owned and operated Folly Faces
- Dec. 4-5 Messiah performances continue holiday tradition at Bluffton and Findlay
- Future Beaver Saturdays invite students to experience Bluffton University
- Ellie Bogart named BHS Student of the Month for October 2026
- Walter "Steve" Suter, 73, worked at Kirtland’s Auto Repair
- Grab an afterschool snack at the Bluffton Public Library