$188,361 street maintenance program on Monday's council agenda
Bluffton council will act on a proposed 2016 street maintenance paving schedule during Monday's meeting.
Heres the street and alley committee 2016 recommendation with estimated costs:
• Kibler Street - $39,697
• Garmatter Street - $57,525
• Harmon Road - Bentley to Garau - $27,781
• Church Street - Main to Jackson - $15,575
• Jackson Street - Church to Elm - $23,970
• Ethan Circle - $16,813
• Striping - $7,000
The original street maintenance budget was 4170,670, however due to a warm winter, council may transer $21,500 from winter funds (salt and snow removal) to the street program.
Several additional items are on Monday's agenda. Those are detailed in the attachement at the bottom of this story.
Stories Posted This Week
Thursday, November 26, 2026
Wednesday, November 25, 2026
- Trolley rides after the Blaze Parade
- Swiss House presents two Christmas workshops
- Football coach hired at Bluffton University
- 2026 Blaze of Lights schedule and businesses open late
- Matthews signs letter of intent with University of Findlay
- Blanchard River Watershed Partnership awards honors for water stewardship
- Bluffton Council recap: Willow Ridge expansion submitted without sidewalks
- Bluffton blazes on November 28 with parade, entertainment, art and lights display