Curbing next step in Bluffton Hospital construction project
Pending weather conditions, curbing work should occur mid-week and driveway pours later in the week in construction projects at Bluffton Hospital.
The canopy roof will be roofed, and the second floor windows plus a few around back should be complete.
Eyebrow boarding should start.
Other projects include:
- Work on the corridor to the second floor will begin.
Surgery Area
- With the surgery floor complete, the contractor should finish drywall mud and finish in this area.
- The plumber should finish medical gas piping and electrical connections to the surgery lights and booms.
- Toward the end of the week, painting may begin.
Two story Emergency area
- Drywall hanging should finish.
- Painting of a dozen or so rooms can occur and more ceiling grid will be hung.
- HVAC diffusers should start to be installed and the porcelain tile installation should begin in the restrooms.
Stories Posted This Week
Thursday, July 30, 2026
- Vaccination clinics in Lima, Aug 3, 5 and 6 by appointment
- Backman’s My Friends is topic for BPL book discussions
- Wanted: Photos of bicycles in the Swiss Settlement
- Monday evening Hummin' & Strummin' Song Circle scheduled
- Time in a Bottle: Biologic aging versus our actual age
- Hyper-local focus of the Ada Icon and Bluffton Icon
- Learn about 92 years of Fett Hardware on Bluffton History Day