Because of COVID-19 Jefferson Street phase 2 won't take place in 2020
Two 2020 Bluffton village projects became victims of COVID-19 on Monday.
Bluffton council placed its Jefferson Street Phase 2 project, scheduled for 2020, on hold, and the council slashed its 2020 street program nearly in half. The action is due to anticipate lower village and state revenues this year.
Council’s finance committee, meeting on April 16, by consensus, agreed to put off the Jefferson Street reconstruction program due to notification from the State of Ohio that all funding is frozen and the uncertainty of village revenues due to state mandated stay at home orders.
The original 2020 street program had a $327,939 price tag. That program was slashed in half and is now a $157,949 expenditure. The before and after street program list is attached at the bottom of this story.
Also at the bottom of this story is Monday's council packet.
Stories Posted This Week
Monday, July 6, 2026
Sunday, July 5, 2026
Saturday, July 4, 2026
Friday, July 3, 2026
- Ada Icon headlines, July 3
- OPEN POLL What's your top traffic safety priority in Bluffton?
- Bluffton University Board of Trustees approves faculty promotion, reviews institutional progress
- Summer Crisis program begins July 1
- Quarry Farm Nature Preserve news for Summer 2026
- Bluffton roundabout opens, Pocono closes at SR 103
- Musical duo learns, performs 50 songs for America 250
- Why Icon Facebook comments are moderated
- June 2026 land transfers in the Bluffton School District
- July 2026 programs and services at Bluffton Public Library
Thursday, July 2, 2026
- Ada Icon headlines, July 2
- Obituary for Lois C. Fischer
- Watercolor Workshop scheduled at Bluffton Public Library
- Mobile Health Clinic coming on July 9
- T-Rex Tea Party at the Bluffton Public Library
- Critters, Flitters, and Gallinippers: SCHS 2nd Saturday, July 11
- Surveyor James Riley will time travel on July 4
- The Air That I Breathe: Air Pollution and Omega-3 Fatty Acids